Key Construction Technologies for Immersed Tunnel of Shenzhen-Zhongshan Link

CHEN Yue1 CHEN Weile1 SONG Shenyou1 LIU Jian1 JIN Wenliang1

(1.Shenzhen-Zhongshan Link Administration Center, Zhongshan, Guangdong, China 528400)

【Abstract】Shenzhen-Zhongshan Crossing-river Link (Shen-Zhong Link) is the key project in G2518 of National Expressway Network, across the Pearl River Estuary. Shen-Zhong Link is a mega project integrating bridges, artificial islands, tunnel, and underwater interchanges, which is built according to the standard for bi-direction eight-lane expressways. The total length of the project is 24 km, of which the tunnel is 6 845 m long, constructed by immersed tube method. Through experimental researches, analysis and demonstration, the technological requirements and construction process for the steel-concrete-steel composite structure of the rectangular immersed tube, the pre-laid gravel cushion and the underwater deep cement mixing (DCM) pile foundation treatment. In addition, a series of special construction equipment, such as the self-propelled huge barge integrated with the floating, towing, immersion and installation functions is developed.

【Keywords】 Shenzhen-Zhongshan Link; immersed tunnel; steel-concrete-steel composite structure; foundation treatment; special construction equipment;

【DOI】

Download this article

    References

    [1] YANG Wenwu. Development of immersed tube tunneling technology [J]. Tunnel Construction, 2009, 29(4): 297.

    [2] RUSSELL Helena. Partnership pays: Project management the Oresund way [M]. Beijing: China Communications Press, 2017.

    [3] WANG Qinghua. Technical analysis of immersed tube tunnel for Busan-Geoje Sea Crossing project [J]. Modern Business Trade Industry, 2009, 21(14): 267.

    [4] LYU Yonggang, Hong Kong-Macao-Zhuhai Bridge immersed tunnel project [J]. Tunnel Construction, 2017, 37 (9): 1193.

    [5] XU Guoping, SU Quanke, LI Zhenxin, et al. Research on key design technology of extra-long immersed tunnel in opensea [J]. Highway, 2015, 60(4): 1.

    [6] JIANG Shuping, SU Quanke, ZHOU Jian, et al. Key technology of disaster prevention and mitigation for offshore extra-long immersed tunnels [M]. Beijing: China Communications Press, 2018.

    [7] XU Guoping, HUANG Qingfei. General design of Shenzhen-Zhongshan River-crossing Link project [J]. Tunnel Construction, 2018, 38(4): 627.

    [8] XIA Fengyong, LIU Hanyong, LIU Jian. Typical construction of steel cylinder sunk by vibration in west artificial island engineering of Shen-Zhong Link [J]. Journal of Highway and Transportation Research and Development (Application Technology), 2018(5): 238.

    [9] CHEN Yue. Application and developing trends of immersed tunnel [J]. Tunnel Construction, 2017, 37(4): 387.

    [10] CHEN Shaozhang, SU Zongxian, CHEN Yue. New technologies used for immersed tunnel of Hong Kong-Zhuhai-Macao Bridge project [J]. Tunnel Construction, 2015, 35(5): 396.

    [11] GAN Pengshan, ZHAO Guohu, YUAN Yong, et al. Study of distribution of transverse foundation stiffness of immersed tunnel [J]. Tunnel Construction, 2018, 38(4): 611.

    [12] ZHANG Zhigang, LIU Hongzhou. Development and key technologies of immersed highway tunnels [ J]. Tunnel Construction, 2013, 33(5): 343.

    [13] CCCC First Harbor Engineering Company Ltd. Handbook for harbour engineering construction: Volume one [M]. 2nd ed. Beijing: China Communications Press, 2015.

This Article

ISSN:2096-4498

CN: 44-1745/U

Vol 40, No. 04, Pages 603-610

April 2020

Downloads:7

Share
Article Outline

Abstract

  • 0 Introduction
  • 1 Introduction of project
  • 2 Objective and philosophy
  • 3 Main technical standards
  • 4 Key construction technologies
  • 5 Conclusions
  • References